– monitoring consumption generated by each single electrical load;
– memorizing consumption data monitored over a time period;
– subdividing the consumption data memorized in a first data group representative of electrical consumption relating to essential services and in a second data group representative of electrical consumption relating to activity of a discontinuous nature;
– determining a minimum value of electrical consumption to guarantee to essential services.
Tipology: Industrial Invention
Application number: 102013902173253 (RE2013A000049)
Application date: 09 July 2013
Publication date: 10 January 2015
Class: H02J3 14
Inventor: Roberto Quadrini
Country: Italy
Grant number: 0001419107
Grant date: 05 November 2015
Tipology: Industrial Invention
Application number: 102013902179506 (RE2013A000056)
Application date: 29 July 2013
Publication date: 30 January 2015
Class: H02J
Inventor: Roberto Quadrini
Country: WIPO | PCT
Application number: WO2015/015267 A1
Application date: 05 February 2015
Country: Italy
Grant number: 0001419109
Grant date: 05 November 2015
Country: Russian Federation
Application number: 2016102418
Application date: 27 January 2016
Grant number: RU2666751 C2
Grant date: 12 September 2018
Country: Europe
Application number: EP3028361
Application date: 08 June 2016
Country: United States of America
Application number: US2016/181804 A1
Application date: 23 June 2016
Grant number: US9991705 B2
Grant date: 05 June 2018
– monitoring the production of electrical energy;
– identifying physical nodes of the electricity grid, where the physical nodes are managed by electric distribution points of the energy produced by the power plants;
– monitoring demand for electrical energy in arrival from a plurality of distribution points;
– subdivision of data relating to electrical energy demand monitored;
– determination of a minimum value of electrical energy to be produced so as to guarantee essential services to the distribution points, and identification of virtual nodes of the electricity power grid, where the virtual nodes exhibit a property of supplying energy to the physical nodes depending on availability of energy generated during a programming step of aggregate electrical withdrawal, due to activities of a discontinuous nature, and not consumed in a reference period.
Tipology: Industrial Invention
Application number: 102013902217218 (RE2013A000092)
Application date: 13 December 2013
Publication date: 14 June 2015
Class: H02J
Inventor: Roberto Quadrini
Country: Italy
Grant number: 0001421371
Grant date: 14 March 2016
– providing the electric load profiles and a carbon dioxide map for each load associated with the single electrical outlet, for each time interval, for each type of electricity supply contract;
– correlating CO2 emission data with weather data and electrical load measurement data;
– providing a short-term emission forecast of the CO2 profile, acquiring, recording and storing all the measured electrical parameters (POD number, electrical contract number, user number, date, current parameter, voltage, active power, reactive power, apparent power, active energy, reactive energy, apparent energy), for a period of 5 years, with accuracy class 0.2S and 0.5 of the electrical variables measured.
Tipology: Utility Model
Application number: MI2011U000188
Application date: 31 May 2011
Publication date: 01 December 2012
Class: H02J
Inventor: Roberto Quadrini
Country: Italy
Grant number: 0000275451
Grant date: 08 April 2013